Watermain Replacement on King Street West

City of Toronto has planned a watermain replacement and Toronto Transit Commission (TTC) streetcar track renewal on King Street West, from Dufferin Street to Close Avenue.

Construction work for this project is expected to take place in five phases, between November 2026 to August 2027. Weather permitting, Phase 1 of the construction will begin on Monday, November 23, with watermain replacement on the north side of King Street West.

There will be road restrictions as part of this construction. During the first two phases of work, one vehicle lane will be maintained in each direction through the work zone between Close Avenue and Dufferin Street.